top of page

How Much Does EV Charging Cost in a NSW Strata Building?

8 minutes ago
4 min read

The NSW Government's residential strata guidance estimates an individual EV charger installation at $2,000 to $5,000, while shared infrastructure for an entire building can cost $75,000 to $200,000.


These estimates cover different scopes of work. For strata committees in Sydney, the first budgeting decision is how many parking bays need charging now and how many should be ready for future connections.


Indicative strata EV charging installation costs in NSW


The NSW Government provides the following approximate costs for residential strata buildings.


Installation approach

Indicative cost (AUD)

Individual EV charger installation

2,000–5,000

Shared charging on common property

20,000–50,000

Modular EV charging infrastructure

5,000–7,000 per readiness box

Whole-of-building infrastructure

75,000–200,000

Individual charger and connection to an existing modular or building-wide EV charging system

2,000–3,000


The modular approach described in the NSW guidance uses readiness boxes or equivalent infrastructure, each supporting approximately six chargers. Individual charging equipment and final connections are additional costs under the modular and whole-of-building approaches.


The government's online funding table does not specify the pricing date or GST treatment. Its earlier residential strata guide from 2022 gives estimates of up to $20,000 for individual installations without existing EV charging infrastructure.


These figures are useful for preliminary budgeting. They are not current installation quotations, maximum project costs or VeCharge prices.


What does an EV charging installation quote include?


A strata EV charging budget needs to account for three categories of expenditure:


  • Shared infrastructure, including electrical assessment, system design, distribution boards and cabling where required.

  • Individual charging equipment, final electrical connections, installation and testing.

  • Operating expenses, including electricity, maintenance and applicable software or billing charges.


The shared system may also need metering, communications equipment and dynamic load management. Depending on the condition and capacity of the building's electrical infrastructure, switchboard or electrical supply upgrades may be necessary.


Infographic titled Three categories of EV charging costs, showing shared infrastructure, individual charger, and ongoing operation in black, white, and orange.

Why EV charger installation costs vary between apartment buildings


Consider two Sydney apartment buildings with the same number of parking bays.


In the first building, a suitable switchboard is close to the parking area. In the second, cables need to reach parking bays across several basement levels, with existing services obstructing the route.


The second installation may require more labour, cabling and supporting electrical works, even if both buildings use identical chargers.


The NSW Government's EV charging costing tool identifies several site-specific factors:


  • Existing switchboard condition and spare capacity.

  • Cable distances and available routes.

  • Trenching and cable support requirements.

  • Potential electricity network upgrades.


Dynamic load management can distribute the available electrical capacity between chargers. Depending on demand, it may reduce the need for capacity upgrades, although electrical supply or switchboard upgrades may still be necessary.


Infographic of Building A vs B EV charging: A has accessible switchboard and short cable route; B has complex route and basements.

Cost per EV-ready parking bay versus cost per connected user


Suppose an owners corporation invests $24,000 in shared electrical infrastructure that prepares 24 parking bays for future charger connections. Initially, four residents install chargers.


Cost metric

Illustrative amount

Shared infrastructure investment

$24,000

Parking bays made EV-ready

24

Initial users

4

Shared infrastructure cost per EV-ready bay

$1,000

Shared infrastructure cost per initial user

$6,000


Neither of these per-bay or per-user amounts includes the individual charger or its final connection. They are financial measures of the shared investment, not mandatory charges payable by residents.


The actual amount each resident pays depends on the funding arrangement agreed for the building.


Infographic comparing EV-ready bay costs: $1,000 per bay, $6,000 per initial user, with 24 bays and 4 users on a dark background.

When comparing installation quotes, check how many parking bays each proposal prepares and what it would cost to connect the next resident.


Who pays for EV charging in a strata building?


Under a shared infrastructure model, the owners corporation may fund the common electrical works, while individual owners pay for their chargers and installations.


The owners corporation may recover some of its initial investment through an agreed funding arrangement. Electricity consumption can be billed separately.


An individual installation may suit a small building with limited demand and suitable electrical capacity. Where more residents are expected to request charging, a staged installation may allow the owners corporation to defer some expenditure.


Before choosing an approach, establish which infrastructure works would need to be repeated when additional residents connect.


Ongoing EV charging costs to include in your budget


Some expenses continue after the chargers are installed. Depending on the system, these may include:


  • Charging management software subscriptions.

  • Connectivity and billing administration.

  • Inspections, servicing and repairs.

  • Equipment replacement.


Ask whether the provider charges a subscription per charger or across the whole building. Confirm which services are included and which will be invoiced separately.


The Australian Government's EV charging guide for owners corporations also covers cost recovery and electricity billing arrangements.


What should a strata committee check before approving the budget?


We recommend asking each installer to provide the following information:


  1. Available electrical capacity and any upgrades required.

  2. Initial cost of the shared infrastructure and the number of EV-ready parking bays.

  3. Cost of connecting an individual parking bay, including charging equipment.

  4. Scope and estimated cost of the next expansion stage.

  5. Recurring charges, GST treatment and exclusions.


Ask installers to quote against the same scope of work. If an electrical upgrade has been excluded because its necessity is still unknown, keep that item open in the budget until it has been assessed.


Planning EV charging for your Sydney apartment building


VeCharge can assess your building's electrical infrastructure and help establish the installation scope before your owners corporation commits to a budget.


Our team designs and installs strata EV charging infrastructure across Sydney, with solutions suited to the building's electrical capacity and expected charging demand.


This article provides general information for NSW strata communities, not legal or electrical engineering advice. Indicative costs are provided for planning purposes and are not installation quotations.

 
 
bottom of page